我需要一种在PHP中添加“工作日”的方法。例如,星期五 12/5 + 3 个工作日 = 星期三 12/10。
至少我需要代码来理解周末,但理想情况下,它也应该考虑到美国联邦假期。如果有必要,我相信我可以通过蛮力提出解决方案,但我希望有一种更优雅的方法。任何人?
谢谢。
我需要一种在PHP中添加“工作日”的方法。例如,星期五 12/5 + 3 个工作日 = 星期三 12/10。
至少我需要代码来理解周末,但理想情况下,它也应该考虑到美国联邦假期。如果有必要,我相信我可以通过蛮力提出解决方案,但我希望有一种更优雅的方法。任何人?
谢谢。
这是PHP手册中date()函数页面上的用户评论中的函数。这是对注释中早期函数的改进,该函数增加了对闰年的支持。
输入开始日期和结束日期,以及可能介于两者之间的任何假日的数组,它将以整数形式返回工作日:
<?php
//The function returns the no. of business days between two dates and it skips the holidays
function getWorkingDays($startDate,$endDate,$holidays){
// do strtotime calculations just once
$endDate = strtotime($endDate);
$startDate = strtotime($startDate);
//The total number of days between the two dates. We compute the no. of seconds and divide it to 60*60*24
//We add one to inlude both dates in the interval.
$days = ($endDate - $startDate) / 86400 + 1;
$no_full_weeks = floor($days / 7);
$no_remaining_days = fmod($days, 7);
//It will return 1 if it's Monday,.. ,7 for Sunday
$the_first_day_of_week = date("N", $startDate);
$the_last_day_of_week = date("N", $endDate);
//---->The two can be equal in leap years when february has 29 days, the equal sign is added here
//In the first case the whole interval is within a week, in the second case the interval falls in two weeks.
if ($the_first_day_of_week <= $the_last_day_of_week) {
if ($the_first_day_of_week <= 6 && 6 <= $the_last_day_of_week) $no_remaining_days--;
if ($the_first_day_of_week <= 7 && 7 <= $the_last_day_of_week) $no_remaining_days--;
}
else {
// (edit by Tokes to fix an edge case where the start day was a Sunday
// and the end day was NOT a Saturday)
// the day of the week for start is later than the day of the week for end
if ($the_first_day_of_week == 7) {
// if the start date is a Sunday, then we definitely subtract 1 day
$no_remaining_days--;
if ($the_last_day_of_week == 6) {
// if the end date is a Saturday, then we subtract another day
$no_remaining_days--;
}
}
else {
// the start date was a Saturday (or earlier), and the end date was (Mon..Fri)
// so we skip an entire weekend and subtract 2 days
$no_remaining_days -= 2;
}
}
//The no. of business days is: (number of weeks between the two dates) * (5 working days) + the remainder
//---->february in none leap years gave a remainder of 0 but still calculated weekends between first and last day, this is one way to fix it
$workingDays = $no_full_weeks * 5;
if ($no_remaining_days > 0 )
{
$workingDays += $no_remaining_days;
}
//We subtract the holidays
foreach($holidays as $holiday){
$time_stamp=strtotime($holiday);
//If the holiday doesn't fall in weekend
if ($startDate <= $time_stamp && $time_stamp <= $endDate && date("N",$time_stamp) != 6 && date("N",$time_stamp) != 7)
$workingDays--;
}
return $workingDays;
}
//Example:
$holidays=array("2008-12-25","2008-12-26","2009-01-01");
echo getWorkingDays("2008-12-22","2009-01-02",$holidays)
// => will return 7
?>
获取两个日期之间没有假期的工作日数:
echo number_of_working_days('2013-12-23', '2013-12-29');
3
function number_of_working_days($from, $to) {
$workingDays = [1, 2, 3, 4, 5]; # date format = N (1 = Monday, ...)
$holidayDays = ['*-12-25', '*-01-01', '2013-12-23']; # variable and fixed holidays
$from = new DateTime($from);
$to = new DateTime($to);
$to->modify('+1 day');
$interval = new DateInterval('P1D');
$periods = new DatePeriod($from, $interval, $to);
$days = 0;
foreach ($periods as $period) {
if (!in_array($period->format('N'), $workingDays)) continue;
if (in_array($period->format('Y-m-d'), $holidayDays)) continue;
if (in_array($period->format('*-m-d'), $holidayDays)) continue;
$days++;
}
return $days;
}